Customer was expanding their facility and wanted to double their production output. Customer was filling product using only traditional bottling methods.
Analysis:
- No prints or layout drawings existed for the new line
- Project needed to be completed in a 6 month window to be ready for their seasonal product
- Existing equipment would have to be refurbished and relocated
- Additional process piping was required
- Needed to integrate a new asceptic sterilized filling system
Solution:
- CHL Systems handled the following:
- Installed over 16,000 feet of process piping
- Reconfigured existing process piping
- Installed asceptic CIP bottling system
- Refurbished numerous pieces of equipment, including tanks, mixers and juice finishers
- Designed and manufactured pumice augers, and grading and incline conveyors
Result:
- Project completed on-time and to the customer’s satisfaction
- Customer now has the capacity to run double their original production output
- Sterilized asceptic filling has augmented their traditional bottle filling system to allow increased capacity and greater product offerings